Field
Local
City of Oakland
City of Oakland Bureau of Building / Public Works Department
Permit
Permit / AuthorizationGrading Permit with C.3 Stormwater Treatment Compliance
Submit ToCity of Oakland Bureau of Building / Public Works Department
Lead TimePlan review 4–8 weeks; C.3 compliance reviewed as part of building/grading permit
Application MethodOnline via City of Oakland permit portal; C.3 stormwater control plan submitted with permit package
FeeIncluded in grading/building permit fees; no separate stormwater fee
Water Quality
Impervious Cover LimitNo citywide cap; C.3 requirements triggered at ≥ 10,000 sq ft of new or replaced impervious surface
On-Site Treatment RequiredYes
Detention RequiredYes — Treat 85th-percentile 24-hour storm using LID; bioretention, permeable pavement, or infiltration; hydromodification management required for most projects per MRP
Turbidity / Discharge StandardMust comply with state CGP and San Francisco Bay Regional Water Board Basin Plan objectives
SWPPP
SWPPP / Local Plan RequiredYes — C.3 Stormwater Management Plan for post-construction; SWPPP per state CGP for construction phase
PE Stamp RequiredYes
Inspections
Inspection RequirementsCity inspects BMP installation during construction. Post-construction C.3 facilities require recorded maintenance agreements, annual self-inspections, and periodic city verification.
Inspector QualificationQSP/QSD per state CGP; no additional city certification
Design & Zones
Local Design ManualAlameda County Clean Water Program C.3 Stormwater Technical Guidance
Special Overlay ZonesOakland Hills Fire Zone, Coastal Zone / Port Area