Compare Regulations

Compare city/county requirements side-by-side (up to 4 jurisdictions)

City of San José(3 more)

Rows with an amber indicator differ across selections.

Field
Local
City of San José
City of San José Department of Public Works / Planning, Building and Code Enforcement (PBCE)
Permit
Permit / AuthorizationGrading Permit with C.3 Stormwater Treatment Requirements
Submit ToCity of San José Department of Public Works / Planning, Building and Code Enforcement (PBCE)
Lead TimePlan review 4–6 weeks; C.3 stormwater compliance reviewed concurrently with grading/building permit
Application MethodOnline via City of San José permit portal; stormwater control plan submitted as part of building/grading package
FeeGrading permit fee based on earthwork volume; stormwater review included in permit fees
Water Quality
Impervious Cover LimitNo citywide cap; C.3 requirements triggered at ≥ 10,000 sq ft of new or replaced impervious surface for regulated projects
On-Site Treatment RequiredYes
Detention RequiredYes — Treat the volume of runoff from the 85th-percentile 24-hour storm using LID measures; bioretention, permeable pavement, or infiltration preferred; hydromodification management plan required for most projects
Turbidity / Discharge StandardMust comply with state CGP Risk Level standards and San Francisco Bay Regional Water Board Basin Plan objectives
SWPPP
SWPPP / Local Plan RequiredYes — C.3 Stormwater Management Plan for post-construction; SWPPP per state CGP for construction phase
PE Stamp RequiredYes
Inspections
Inspection RequirementsCity inspects BMP installation during construction. Post-construction BMPs require annual self-inspection and reporting. City conducts periodic compliance inspections.
Inspector QualificationQSP/QSD per state CGP; city does not require additional local certification
Design & Zones
Local Design ManualSanta Clara Valley Urban Runoff Pollution Prevention Program (SCVURPPP) C.3 Stormwater Handbook
Special Overlay ZonesRiparian Corridor, Flood Zone