Compare Regulations

Compare city/county requirements side-by-side (up to 4 jurisdictions)

Nassau County(3 more)

Rows with an amber indicator differ across selections.

Field
Local
Nassau County
Nassau County Department of Public Works / Individual town/village building departments
Permit
Permit / AuthorizationNassau County DPW Stormwater Management Approval / Town-level Building Permit
Submit ToNassau County Department of Public Works / Individual town/village building departments
Lead TimeCounty stormwater review 4–8 weeks; town permits concurrent
Application MethodCounty stormwater plans submitted to Nassau County DPW; building permits via individual town/village
FeeCounty review fees vary; town permit fees per project scope
Water Quality
Impervious Cover LimitNo countywide cap; post-construction management required per NYSDEC MS4 permit; county reviews drainage for projects impacting county infrastructure
On-Site Treatment RequiredYes
Detention RequiredYes — Manage the first 1 inch of rainfall on-site per NYS Stormwater Management Design Manual; leaching basins and drywells historically common on Long Island due to sandy soils
Turbidity / Discharge StandardMust comply with NYSDEC SPDES CGP; Long Island Sound and South Shore Estuary protections apply
SWPPP
SWPPP / Local Plan RequiredYes — SWPPP per NYSDEC; drainage/stormwater plan per Nassau County DPW for projects affecting county drainage infrastructure
PE Stamp RequiredYes
Inspections
Inspection RequirementsTown/village inspections at permit milestones. County DPW inspects stormwater facilities connected to county drainage. Post-construction BMPs require maintenance agreements.
Inspector QualificationNYSDEC-approved QI/TC per SPDES CGP; no additional county certification
Design & Zones
Local Design ManualNYS Stormwater Management Design Manual / Nassau County DPW Standards
Special Overlay ZonesSole Source Aquifer / Groundwater Protection, South Shore Estuary Reserve