City of Amarillo
City of Amarillo Engineering Department / Development Services
Permit
Permit / AuthorizationGrading / Site Development Permit
Submit ToCity of Amarillo Engineering Department / Development Services
Lead TimePlan review typically 2–4 weeks for standard projects
Application MethodSubmit via City of Amarillo Development Services online portal or in person at City Hall, 601 S. Buchanan St., Amarillo, TX 79101
FeeContact agency for current fee schedule
Water Quality
Impervious Cover LimitNo citywide impervious cover cap; drainage systems must accommodate design storm flows per Amarillo Drainage Design Criteria
On-Site Treatment RequiredNo
Detention RequiredYes — Detention required to limit post-development peak flows to pre-development levels for 2-, 10-, and 100-year storms per City of Amarillo Drainage Design Criteria Manual
Turbidity / Discharge StandardNo numeric NTU limit; discharges must comply with TCEQ TXR150000; wind erosion controls are equally important given Panhandle wind conditions
SWPPP
SWPPP / Local Plan RequiredYes — SWPPP per TCEQ TXR150000; drainage report required for local permit
PE Stamp RequiredYes
Inspections
Inspection RequirementsCity of Amarillo Engineering Department inspects grading permits at rough grading and final stabilization. Spring thunderstorm season (April–June) requires active BMP maintenance.
Inspector QualificationNo city-specific certification required beyond TCEQ SWPPP requirements
Design & Zones
Local Design ManualCity of Amarillo Drainage Design Criteria Manual
Special Overlay ZonesCanadian River Watershed, FEMA Special Flood Hazard Area (SFHA)