Compare Regulations

Compare city/county requirements side-by-side (up to 4 jurisdictions)

City of Bryan(3 more)

Rows with an amber indicator differ across selections.

Field
Local
City of Bryan
City of Bryan Public Works / Engineering
Permit
Permit / AuthorizationGrading / Drainage Permit
Submit ToCity of Bryan Public Works / Engineering
Lead TimePlan review typically 2–4 weeks
Application MethodSubmit via City of Bryan Development Services at 300 S. Texas Ave., Bryan, TX 77803 or online portal at bryantx.gov
FeeContact agency for current fee schedule
Water Quality
Impervious Cover LimitNo citywide impervious cover cap; drainage systems must accommodate design storm flows per City of Bryan Drainage Design Criteria; Navasota River and Brazos River receive Bryan-area stormwater
On-Site Treatment RequiredNo
Detention RequiredYes — Detention required to limit post-development peak flows to pre-development levels for 2-, 10-, and 100-year storms per City of Bryan Drainage Design Criteria; Brazos County drainage district requirements may apply for county channel connections
Turbidity / Discharge StandardNo numeric NTU limit; discharges must comply with TCEQ TXR150000 and not degrade Navasota River, Brazos River, or Gibbons Creek water quality
SWPPP
SWPPP / Local Plan RequiredYes — SWPPP per TCEQ TXR150000; drainage report required for local permit
PE Stamp RequiredYes
Inspections
Inspection RequirementsCity of Bryan Public Works inspects grading permits at rough grading and final stabilization.
Inspector QualificationNo city-specific certification required beyond TCEQ SWPPP requirements
Design & Zones
Local Design ManualCity of Bryan Drainage Design Criteria
Special Overlay ZonesNavasota River Watershed, FEMA Special Flood Hazard Area