Compare city/county requirements side-by-side (up to 4 jurisdictions)

City of El Paso(3 more)

Rows with an amber indicator differ across selections.

Field
Local
City of El Paso
City of El Paso Development Services Department (DSD)
Permit
Permit / AuthorizationGrading / Land Disturbance Permit
Submit ToCity of El Paso Development Services Department (DSD)
Lead TimePlan review typically 2–4 weeks; permit issued before grading begins
Application MethodOnline via El Paso permitting portal (elpasotexas.gov) or in-person at DSD
FeeBased on disturbed area and project valuation; contact DSD for current schedule
Water Quality
Impervious Cover LimitNo citywide impervious cover cap; drainage infrastructure must convey design storm flows
On-Site Treatment RequiredYes
Detention RequiredYes — Detention required to limit post-development peak flows to pre-development levels for 2-, 10-, and 100-year storms per El Paso Stormwater Management and Design Manual
Turbidity / Discharge StandardNo numeric NTU limit in local ordinance; discharges must comply with TCEQ TXR150000 and not violate Rio Grande water quality standards
SWPPP
SWPPP / Local Plan RequiredYes — Stormwater Pollution Prevention Plan (SWPPP) — aligned with TCEQ TXR150000; local ESC plan as part of grading permit
PE Stamp RequiredYes
Inspections
Inspection RequirementsCity of El Paso DSD inspects grading permits independently of TCEQ. Inspections required at key milestones: rough grading, drainage structure installation, final stabilization. Complaint-driven inspections also conducted.
Inspector QualificationNo city-specific certification beyond TCEQ requirements; contractor responsible for SWPPP implementation
Design & Zones
Local Design ManualEl Paso Stormwater Management and Design Manual
Special Overlay ZonesRio Grande Floodplain (FEMA AE/AO Zones), Desert Arroyo / Wash Corridors, International Border Zone