Compare city/county requirements side-by-side (up to 4 jurisdictions)

City of Garland(3 more)

Rows with an amber indicator differ across selections.

Field
Local
City of Garland
City of Garland Development Services
Permit
Permit / AuthorizationGrading / Drainage Permit
Submit ToCity of Garland Development Services
Lead TimePlan review typically 2–4 weeks
Application MethodSubmit via City of Garland Development Services at 800 Main St., Garland, TX 75040 or online portal
FeeContact agency for current fee schedule
Water Quality
Impervious Cover LimitNo citywide impervious cover cap; drainage systems must accommodate design storm flows per City of Garland Engineering Standards
On-Site Treatment RequiredNo
Detention RequiredYes — Detention required to limit post-development peak flows to pre-development levels for 2-, 10-, and 100-year storms per City of Garland Drainage Design Criteria; Lake Ray Hubbard watershed considerations apply for projects draining eastward
Turbidity / Discharge StandardNo numeric NTU limit; discharges must comply with TCEQ TXR150000 and not degrade Lake Ray Hubbard or Duck Creek
SWPPP
SWPPP / Local Plan RequiredYes — SWPPP per TCEQ TXR150000; drainage report required for local permit
PE Stamp RequiredYes
Inspections
Inspection RequirementsCity of Garland Development Services inspects grading permits at rough grading and final stabilization. Lake Ray Hubbard watershed sensitivity requires active BMP maintenance.
Inspector QualificationNo city-specific certification required beyond TCEQ SWPPP requirements
Design & Zones
Local Design ManualCity of Garland Engineering Standards
Special Overlay ZonesLake Ray Hubbard Watershed Protection Area, Duck Creek Floodplain