City of Harlingen Public Works / Engineering
Permit
Permit / AuthorizationGrading / Drainage Permit
Submit ToCity of Harlingen Public Works / Engineering
Lead TimePlan review typically 2–4 weeks
Application MethodSubmit via City of Harlingen Building Department at 118 E. Tyler Ave., Harlingen, TX 78550 or contact city engineering
FeeContact agency for current fee schedule
Water Quality
Impervious Cover LimitNo citywide impervious cover cap; drainage systems must accommodate design storm flows per City of Harlingen Drainage Design Criteria; flat RGV topography requires pump-assisted drainage in low areas
On-Site Treatment RequiredNo
Detention RequiredYes — Detention required to limit post-development peak flows to pre-development levels for 2-, 10-, and 100-year storms per City of Harlingen Drainage Design Criteria; Rio Grande Valley irrigation canals and the Cameron County Drainage District system are interconnected with urban stormwater
Turbidity / Discharge StandardNo numeric NTU limit; discharges must comply with TCEQ TXR150000 and not degrade Arroyo Colorado or Rio Grande water quality
SWPPP
SWPPP / Local Plan RequiredYes — SWPPP per TCEQ TXR150000; drainage report required for local permit
PE Stamp RequiredYes
Inspections
Inspection RequirementsCity of Harlingen Public Works inspects grading permits at rough grading and final stabilization.
Inspector QualificationNo city-specific certification required beyond TCEQ SWPPP requirements
Design & Zones
Local Design ManualCity of Harlingen Drainage Design Criteria
Special Overlay ZonesArroyo Colorado (Impaired Waterway), Cameron County Irrigation / Drainage Districts, FEMA Special Flood Hazard Area