Compare Regulations

Compare city/county requirements side-by-side (up to 4 jurisdictions)

City of Lewisville(3 more)

Rows with an amber indicator differ across selections.

Field
Local
City of Lewisville
City of Lewisville Development Services
Permit
Permit / AuthorizationGrading / Drainage Permit
Submit ToCity of Lewisville Development Services
Lead TimePlan review typically 2–4 weeks
Application MethodSubmit via City of Lewisville Development Services at 151 W. Church St., Lewisville, TX 75057 or online portal
FeeContact agency for current fee schedule
Water Quality
Impervious Cover LimitNo citywide impervious cover cap; drainage systems must accommodate design storm flows per Lewisville Drainage Design Criteria; Lewisville Lake watershed is a primary concern
On-Site Treatment RequiredNo
Detention RequiredYes — Detention required to limit post-development peak flows to pre-development levels for 2-, 10-, and 100-year storms per City of Lewisville Drainage Design Criteria
Turbidity / Discharge StandardNo numeric NTU limit; discharges must comply with TCEQ TXR150000 and not degrade Lewisville Lake, Elm Fork Trinity River, or downstream water quality
SWPPP
SWPPP / Local Plan RequiredYes — SWPPP per TCEQ TXR150000; drainage report required for local permit
PE Stamp RequiredYes
Inspections
Inspection RequirementsCity of Lewisville Development Services inspects grading permits at rough grading and final stabilization.
Inspector QualificationNo city-specific certification required beyond TCEQ SWPPP requirements
Design & Zones
Local Design ManualCity of Lewisville Drainage Design Criteria
Special Overlay ZonesLewisville Lake USACE Project Boundary, Elm Fork Trinity River Floodplain