Compare Regulations
Compare state baseline against local requirements in a single view
Loading...
Compare state baseline against local requirements in a single view
Rows with an amber indicator differ across selections.
| Field | State California SWRCB | Local City of Sacramento City of Sacramento Community Development Department / Department of Utilities |
|---|---|---|
| Permit | ||
| Permit / Authorization | Construction General Permit (Order 2009-0009-DWQ, as amended) | Grading Permit with Stormwater Quality Design Manual Compliance |
| Submit To | SWRCB | City of Sacramento Community Development Department / Department of Utilities |
| Lead Time | NOI must be filed and permit coverage obtained before grading/construction begins | Plan review 3–6 weeks; stormwater compliance review concurrent with grading/building permit |
| Application Method | Online via Stormwater Multiple Application and Report Tracking System (SMARTS) | Online via City of Sacramento Accela portal; stormwater quality plan submitted with permit application |
| Fee | Annual fee based on acreage: < 5 acres = $900; 5–49 acres = $1,200; ≥ 50 acres = $2,200 | Grading permit fee based on project area and earthwork; stormwater review fee included |
| Water Quality | ||
| Impervious Cover Limit | No statewide limit | No citywide cap; projects creating or replacing ≥ 5,000 sq ft of impervious surface trigger LID requirements |
| On-Site Treatment Required | Not specified at state level | Yes |
| Detention Required | Not specified at state level | Yes — Treat runoff from the 85th-percentile 24-hour storm using LID measures; infiltration required where feasible given Central Valley clay soils; detention/retention or biofiltration alternatives accepted |
| Turbidity / Discharge Standard | Risk Level 3 sites: effluent must meet 10 NTU turbidity limit at discharge point; Risk Level 2: 250 NTU; Risk Level 1: narrative standard | Must comply with state CGP Risk Level standards and Central Valley Regional Water Board Basin Plan |
| SWPPP | ||
| SWPPP / Local Plan Required | Yes | Yes — Grading-phase Erosion and Sediment Control Plan; post-construction Stormwater Quality Design Plan |
| PE Stamp Required | No | Yes |
| Inspections | ||
| Inspection Requirements | Risk Level 1: Visual inspections every 24 hours during active rain. Risk Level 2–3: Rain Event Action Plans required; inspections during and after qualifying storms | City conducts grading and erosion control inspections during construction. Post-construction LID facilities require recorded maintenance agreements and annual self-inspections. |
| Inspector Qualification | Qualified SWPPP Practitioner (QSP) for Risk Level 2 and 3 sites; Qualified SWPPP Developer (QSD) must prepare the SWPPP | QSP/QSD per state CGP; no additional city-specific certification |
| Design & Zones | ||
| Local Design Manual | N/A — state level | City of Sacramento Stormwater Quality Design Manual |
| Special Overlay Zones | N/A — see local jurisdictions | Flood Zone / Levee-Protected Area, American River Parkway Buffer |