| Field | State Texas TCEQ | Local Comal County (Unincorporated) Comal County Development Services |
|---|---|---|
| Permit | ||
| Permit / Authorization | Construction General Permit (TXR150000) | Floodplain Development Permit / Drainage Review |
| Submit To | TCEQ | Comal County Development Services |
| Lead Time | Must file NOI and receive authorization before construction begins | Plan review typically 2–4 weeks |
| Application Method | Online via TCEQ Water Quality ePay system | Submit via Comal County Development Services at 150 N. Seguin Ave., New Braunfels, TX 78130 or contact county engineering |
| Fee | $325 for projects disturbing < 5 acres; $525 for ≥ 5 acres | Contact agency for current fee schedule |
| Water Quality | ||
| Impervious Cover Limit | No statewide limit | Significant portions of unincorporated Comal County are within the Edwards Aquifer Recharge Zone or Contributing Zone — EAA permit required; impervious cover limits and water quality controls apply on regulated land; western portions of the county are over the recharge zone |
| On-Site Treatment Required | Not specified at state level | No |
| Detention Required | Not specified at state level | Yes — Detention required to limit post-development peak flows to pre-development levels per Comal County Drainage Criteria; applies in unincorporated areas; design must account for Hill Country flash flood risk from Guadalupe and Blanco river watersheds |
| Turbidity / Discharge Standard | Not specified in CGP; discharges must not cause or contribute to violations of water quality standards | No numeric NTU limit; discharges must comply with TCEQ TXR150000 and not degrade Guadalupe River, Comal River, Blanco River, or Edwards Aquifer recharge features |
| SWPPP | ||
| SWPPP / Local Plan Required | Yes | Yes — SWPPP per TCEQ TXR150000; drainage report required for county permits |
| PE Stamp Required | No | Yes |
| Inspections | ||
| Inspection Requirements | Every 14 days and within 24 hours of a rainfall event producing ≥ 0.5 inches | Comal County Development Services inspects development in unincorporated areas. |
| Inspector Qualification | Stormwater Pollution Prevention Plan (SWPPP) Inspector — no state license required but must be knowledgeable | No county-specific certification required beyond TCEQ SWPPP requirements |
| Design & Zones | ||
| Local Design Manual | N/A — state level | Comal County Drainage Criteria |
| Special Overlay Zones | N/A — see local jurisdictions | Edwards Aquifer Recharge Zone (Western Comal County), Guadalupe River Canyon Floodplain, Blanco River Floodplain |