| Field | State Texas TCEQ | Local City of Tyler City of Tyler Development Services |
|---|---|---|
| Permit | ||
| Permit / Authorization | Construction General Permit (TXR150000) | Grading / Drainage Permit |
| Submit To | TCEQ | City of Tyler Development Services |
| Lead Time | Must file NOI and receive authorization before construction begins | Plan review typically 2–4 weeks |
| Application Method | Online via TCEQ Water Quality ePay system | Submit via City of Tyler Development Services at 212 N. Bonner Ave., Tyler, TX 75702 or online portal at cityoftyler.org |
| Fee | $325 for projects disturbing < 5 acres; $525 for ≥ 5 acres | Contact agency for current fee schedule |
| Water Quality | ||
| Impervious Cover Limit | No statewide limit | No citywide impervious cover cap; drainage systems must accommodate design storm flows per City of Tyler Drainage Design Criteria; Lake Tyler and Lake Palestine are important water supply concerns |
| On-Site Treatment Required | Not specified at state level | No |
| Detention Required | Not specified at state level | Yes — Detention required to limit post-development peak flows to pre-development levels for 2-, 10-, and 100-year storms per City of Tyler Drainage Design Criteria; sandy East Texas soils have high infiltration capacity but can also be highly erodible |
| Turbidity / Discharge Standard | Not specified in CGP; discharges must not cause or contribute to violations of water quality standards | No numeric NTU limit; discharges must comply with TCEQ TXR150000 and not degrade Lake Tyler, Lake Palestine, or Mud Creek water quality |
| SWPPP | ||
| SWPPP / Local Plan Required | Yes | Yes — SWPPP per TCEQ TXR150000; drainage report required for local permit |
| PE Stamp Required | No | Yes |
| Inspections | ||
| Inspection Requirements | Every 14 days and within 24 hours of a rainfall event producing ≥ 0.5 inches | City of Tyler Development Services inspects grading permits at rough grading and final stabilization. Sandy East Texas soils require especially attentive BMP maintenance. |
| Inspector Qualification | Stormwater Pollution Prevention Plan (SWPPP) Inspector — no state license required but must be knowledgeable | No city-specific certification required beyond TCEQ SWPPP requirements |
| Design & Zones | ||
| Local Design Manual | N/A — state level | City of Tyler Drainage Design Criteria |
| Special Overlay Zones | N/A — see local jurisdictions | Lake Tyler Watershed Protection Area, Lake Palestine Watershed, FEMA Special Flood Hazard Area |