Compare state-level permit requirements side-by-side (up to 4 states)

AL(3 more)

Rows with an amber indicator differ across selected states.

Field
AL
Alabama
NPDES ProgramState-Delegated
Permitting AgencyAlabama Department of Environmental Management (ADEM)
Permit NameNPDES General Permit ALR100000 (Construction General Permit)
Construction Threshold≥ 1 acre of land disturbance, or < 1 acre if part of a larger common plan of development or sale
NOI Lead TimeNOI must be submitted and permit coverage obtained at least 2 days before construction activity begins
Application MethodPaper NOI submission to ADEM Water Division; online submission available through ADEM e-Portal for some permit types
Permit Fee$0 — Alabama does not charge a permit fee for the construction general permit NOI
SWPPP RequiredYes
PE Certification RequiredNo
SWPPP Template AvailableYes
Inspection FrequencyAt least every 14 calendar days and within 24 hours of a storm event that produces 0.5 inches or more of rainfall at the site
Inspector QualificationInspections must be performed by a qualified person with construction stormwater knowledge; Alabama does not have a state-specific inspector certification program, but the inspector must be familiar with BMPs and the SWPPP
Post-Construction RequiredYes
Turbidity StandardNo numeric NTU limit in the construction general permit; narrative water quality standard applies