Compare Regulations

Compare state-level permit requirements side-by-side (up to 4 states)

CA(3 more)

Rows with an amber indicator differ across selected states.

Field
CA
California
NPDES ProgramState-Delegated
Permitting AgencyState Water Resources Control Board (SWRCB)
Permit NameConstruction General Permit (Order 2009-0009-DWQ, as amended)
Construction Threshold≥ 1 acre of land disturbance (or < 1 acre if part of a larger common plan)
NOI Lead TimeNOI must be filed and permit coverage obtained before grading/construction begins
Application MethodOnline via Stormwater Multiple Application and Report Tracking System (SMARTS)
Permit FeeAnnual fee based on acreage: < 5 acres = $900; 5–49 acres = $1,200; ≥ 50 acres = $2,200
SWPPP RequiredYes
PE Certification RequiredNo
SWPPP Template AvailableYes
Inspection FrequencyRisk Level 1: Visual inspections every 24 hours during active rain. Risk Level 2–3: Rain Event Action Plans required; inspections during and after qualifying storms
Inspector QualificationQualified SWPPP Practitioner (QSP) for Risk Level 2 and 3 sites; Qualified SWPPP Developer (QSD) must prepare the SWPPP
Post-Construction RequiredYes
Turbidity StandardRisk Level 3 sites: effluent must meet 10 NTU turbidity limit at discharge point; Risk Level 2: 250 NTU; Risk Level 1: narrative standard