Compare Regulations

Compare state-level permit requirements side-by-side (up to 4 states)

FL(3 more)

Rows with an amber indicator differ across selected states.

Field
FL
Florida
NPDES ProgramState-Delegated
Permitting AgencyFlorida Department of Environmental Protection (FDEP)
Permit NameGeneric Permit for Stormwater Discharge from Large and Small Construction Activities
Construction Threshold≥ 1 acre of land disturbance (or < 1 acre if part of a larger common plan)
NOI Lead TimeNOI must be submitted at least 2 business days before construction begins
Application MethodOnline via FDEP's ePermitting system (www.fldepportal.com)
Permit Fee$400 for projects < 5 acres; $600 for ≥ 5 acres; additional fees may apply for ERP
SWPPP RequiredYes
PE Certification RequiredNo
SWPPP Template AvailableYes
Inspection FrequencyAt least every 7 days and within 24 hours of a storm event producing ≥ 0.5 inches of rainfall in a 24-hour period
Inspector QualificationStormwater Pollution Prevention Inspector — no specific state certification required, but must be trained and knowledgeable in stormwater BMPs
Post-Construction RequiredYes
Turbidity StandardDischarges must not cause turbidity in receiving waters to exceed 29 NTU above background in Class III waters