Compare Regulations

Compare state-level permit requirements side-by-side (up to 4 states)

LA(3 more)

Rows with an amber indicator differ across selected states.

Field
LA
Louisiana
NPDES ProgramState-Delegated
Permitting AgencyLouisiana Department of Environmental Quality (LDEQ)
Permit NameLPDES Construction Stormwater General Permit (Permit LAR100000)
Construction Threshold≥ 1 acre of land disturbance; < 1 acre if part of a larger common plan of development or sale that will disturb ≥ 1 acre in total
NOI Lead TimeNotice of Intent (NOI) must be submitted to LDEQ at least 2 days before commencement of construction activities; permit coverage is effective 2 days after a complete NOI is received; some sensitive areas may require a longer review period
Application MethodOnline via LDEQ's Electronic Document Management System (EDMS) portal at https://edms.deq.louisiana.gov/; paper NOI also accepted and submitted to LDEQ's Water Permits Division in Baton Rouge
Permit Fee$100 per NOI submission (flat administrative processing fee); no acreage-scaled fee for the construction general permit
SWPPP RequiredYes
PE Certification RequiredNo
SWPPP Template AvailableYes
Inspection FrequencyAt least every 7 days and within 24 hours after a storm event resulting in a discharge from the site; inspection frequency may be reduced to every 14 days for portions of the site that have achieved temporary or final stabilization
Inspector QualificationInspections must be conducted by a qualified inspector who is knowledgeable in the principles and practice of stormwater pollution prevention; LDEQ does not require a specific state-issued inspector certification for construction stormwater, though Certified Inspector of Sediment and Erosion Control (CISEC) or CESSWI credentials are recognized industry standards
Post-Construction RequiredYes
Turbidity StandardNo numeric NTU effluent limit in General Permit LAR100000; narrative water quality standards apply