Compare Regulations

Compare state-level permit requirements side-by-side (up to 4 states)

MO(3 more)

Rows with an amber indicator differ across selected states.

Field
MO
Missouri
NPDES ProgramState-Delegated
Permitting AgencyMissouri Department of Natural Resources (MDNR)
Permit NameNPDES/SDS Land Disturbance General Permit (MOR100000)
Construction Threshold≥ 1 acre of total land disturbance (or < 1 acre if part of a larger common plan of development or sale that will ultimately disturb ≥ 1 acre); also applies to any earth-disturbing activity that the Director determines has the potential to cause water quality violations
NOI Lead TimeLand Disturbance Permit (LDP) application and NOI must be submitted and authorization received before any land-disturbing activities begin. Missouri requires a minimum 2-business-day processing period for complete applications; applicants should allow 5–10 business days in practice
Application MethodOnline via Missouri's Environmental Online Permitting System (myMOEnvironment portal at my.moenv.org); paper applications also accepted at MDNR regional offices
Permit Fee$75 application fee for disturbances < 5 acres; $150 for 5–10 acres; $225 for > 10 acres; annual renewal fees apply if permit coverage extends beyond one year
SWPPP RequiredYes
PE Certification RequiredNo
SWPPP Template AvailableYes
Inspection FrequencyAt least every 14 days and within 24 hours after any measurable precipitation event (defined as ≥ 0.5 inches of rainfall in a 24-hour period). Inspections must also be conducted after any snowmelt that causes a discharge.
Inspector QualificationMissouri requires that at least one Certified Erosion, Sediment and Stormwater Inspector (CESSI) be identified for each project. CESSI certification is obtained through MDNR-approved training programs (e.g., CPESC, CESSWI, or equivalent). This is a state-mandated certification requirement, making Missouri one of the more stringent states for inspector qualifications.
Post-Construction RequiredYes
Turbidity StandardNo numeric NTU effluent limit in the Land Disturbance General Permit MOR100000