MS
Mississippi
NPDES ProgramState-Delegated
Permitting AgencyMississippi Department of Environmental Quality (MDEQ)
Permit NameNPDES General Permit for Stormwater Discharges from Construction Sites (MSR100000)
Construction Threshold≥ 1 acre of land disturbance (or < 1 acre if part of a larger common plan of development or sale that will ultimately disturb ≥ 1 acre)
NOI Lead TimeNOI must be submitted and MDEQ authorization received before construction begins; no fixed statutory lead time, but applicants should allow 7–14 days for processing
Application MethodPaper NOI submission to MDEQ Office of Pollution Control; MDEQ has pursued online submittal enhancements — verify current portal status at mdeq.ms.gov
Permit FeeNo permit fee for coverage under the Construction General Permit MSR100000
SWPPP RequiredYes
PE Certification RequiredNo
SWPPP Template AvailableYes
Inspection FrequencyAt least every 14 days and within 24 hours after any rainfall event of ≥ 0.5 inches during a 24-hour period
Inspector QualificationNo state-mandated certification; inspections must be conducted by a qualified personnel who is knowledgeable about the permit and SWPPP requirements. MDEQ recommends familiarity with BMP installation and maintenance.
Post-Construction RequiredYes
Turbidity StandardNo numeric NTU effluent limit in the Construction General Permit