SW

Stormwater Directory

Compare Regulations

Compare state-level permit requirements side-by-side (up to 4 states)

VA(3 more)

Rows with an amber indicator differ across selected states.

Field
VA
Virginia
NPDES ProgramState-Delegated
Permitting AgencyVirginia Department of Environmental Quality (VDEQ)
Permit NameGeneral VPDES Permit for Discharges of Stormwater from Construction Activities (VAR10)
Construction Threshold≥ 1 acre of land disturbance (or < 1 acre if part of a larger common plan of development or sale that will ultimately disturb ≥ 1 acre)
NOI Lead TimeNOI must be submitted and permit coverage obtained at least 7 days before land disturbance begins; operator must wait for permit coverage confirmation from VDEQ before commencing disturbance
Application MethodOnline via VDEQ's ePermitting portal (VDEQ Online Services); paper NOI also accepted
Permit Fee$750 base registration statement fee for projects < 1 acre (common plan); $750 for 1–5 acres; $1,000 for 5–10 acres; $2,000 for 10–50 acres; $3,000 for ≥ 50 acres (fees established under 9VAC25-870)
SWPPP RequiredYes
PE Certification RequiredNo
SWPPP Template AvailableYes
Inspection FrequencyAt least once every 14 calendar days and within 48 hours following any runoff-producing storm event; inspections must be conducted during normal business hours unless a rainfall event occurs outside those hours
Inspector QualificationInspections must be conducted by or under the oversight of a Responsible Land Disturber (RLD) — a state-issued certification from VDEQ. RLD certification requires completion of a VDEQ-approved training course and passing an exam. The RLD is also responsible for SWPPP implementation.
Post-Construction RequiredYes
Turbidity StandardNo specific numeric NTU limit in the construction general permit; discharges must not cause or contribute to violations of Virginia Water Quality Standards (9VAC25-260)