Arizona
Arizona Department of Environmental Quality
Quick Summary
For most Arizona projects disturbing 1 acre or more, you need a state Construction General Permit and a SWPPP with BMPs tailored to arid desert conditions. The permit fee is $500–$750.
Construction Permit
Permit Document ↗- Permit Name
- Arizona Pollutant Discharge Elimination System (AZPDES) Construction General Permit (CGP) — Permit No. AZG2025-001 (effective 2025, expires August 28, 2030)
- Threshold
- ≥ 1 acre of land disturbance, or < 1 acre if part of a larger common plan of development or sale
- NOI Lead Time
- NOI must be submitted and a permit authorization number received before land disturbance begins; ADEQ typically processes NOIs within 5 business days. Existing permittees under AZG2020-001 must submit a new NOI — coverage does not automatically transfer.
- Application Method
- Online via ADEQ's myDEQ portal (azdeq.gov); paper NOI forms also accepted
- Fee
- $500 for sites disturbing ≥ 1 acre and < 5 acres; $750 for ≥ 5 acres; fee is per project
- Permit Expires
- August 28, 2030
SWPPP Requirements
Permit Document ↗- SWPPP Required
- Yes
- PE Cert Required
- No
- Template Available
- Yes
Inspection Requirements
Permit Document ↗- Frequency
- At least every 14 calendar days and within 24 hours of a storm event that produces 0.5 inches or more of rainfall at the site; in arid regions, inspection frequency may be adjusted if site conditions warrant
- Rain Trigger
- Within 24 hours of a storm event producing ≥ 0.5 inches of rainfall in a 24-hour period
- Inspector Qualification
- Inspections must be performed by a trained individual with knowledge of construction stormwater requirements. Arizona does not require a state-specific certification for inspectors. The permittee or a designated representative familiar with the SWPPP may conduct inspections.
- Accepted Certifications
- No state-specific cert required; inspector must be trained and knowledgeable; CPESC, CESSWI, CISEC accepted
Discharge Standards
Permit Document ↗- Turbidity Limit
- No numeric NTU limit in the CGP; narrative water quality standard applies
Post-Construction
ADEQ ↗- Required
- Yes
Impaired Waterbody / TMDL Requirements
Standard ProvisionsArizona's AZPDES construction permit has standard provisions. No specific permit conditions are triggered by 303(d)-listed waters in the general permit text; standard stormwater BMPs apply. Projects in sensitive desert washes and riparian areas should consult ADEQ directly.
Program Contact
Contact Page ↗- Phone
- (602) 771-1440
State-Specific Notes
Arizona's arid climate means construction sites may go weeks without rain, but the intense monsoon season (July–September) demands fully operational BMPs. ADEQ uses the AZPDES permit numbering system (not NPDES). AZG2025-001 replaced AZG2020-001 (which had replaced AZG2016-001); coverage under prior permits does not automatically transfer — a new NOI must be submitted via the myDEQ portal. The permit expires August 28, 2030. Projects on tribal lands may require coverage under EPA's federal CGP rather than the AZPDES permit.